I-5 Corridor Reinforcement Project would have placed 3.6 miles of high-voltage, overhead power lines through Camas and Washougal

By
timestamp icon
category icon News

More than four years after Camas leaders urged Bonneville Power Administration (BPA) officials to reconsider plans to place high-voltage transmission lines on an 80-mile stretch of land winding through Southwest Washington and Northwest Oregon, the controversial project has come to halt.

BPA officials announced today that they will not build the I-5 Corridor Reinforcement Project, which would have sited 3.6 miles of 500-kilovolt transmission lines within Washougal’s Urban Growth Area, across the Washougal River, into Camas’ Groot Park region and across the Columbia River from Camas to Troutdale, Oregon.